Centralized wastewater collection system in the industrial zone with culvert diameter D400 – D600 mm, total pipe length about 8,336m. 100% of wastewater generated from production activities of tenants in Long Binh Industrial Park is connected to the centralized wastewater collection system of the Industrial Park and flows to the centralized wastewater treatment plant of the Industrial Park for treatment.
The concentrated wastewater treatment plant in Long Binh Industrial Park with a total design capacity of 10,500m3/day.night is divided into 03 modules operating in parallel, in which:
+ Module 1: 2,500 m3/day.night (operated since 1998 with a capacity of 1,500 m3/day.night and renovated the treatment part. biological capacity increased to 2,500 m3/day.night came into operation in 2012).
+ Module 2: 4,000m3/day.night (operated in 2008).
+ Module 3: 4,000m3/day.night (operating in 2010).
LOTECO Industrial Park Wastewater Treatment Plant |
|
Automatic monitoring system of input parameters of the concentrated wastewater treatment plant in Long Binh Industrial Park (COD, color, pH, TSS, temperature). | |
Automatic monitoring system of output parameters of the centralized wastewater treatment plant of Long Binh Industrial Park (COD, pH, DO, TSS, temperature). |
In addition, LOTECO has built 03 hazardous waste warehouses with a total area of 1,345 m2 , 01 domestic waste warehouse of 11.5 m2 and construction to prevent and respond to environmental incidents for wastewater for the concentrated wastewater treatment plant of Long Binh Industrial Park according to regulations, LOTECO operates the wastewater treatment system, supports, troubleshoots, and advises on environmental related issues for customers in the LOTECO IZ 24/7.